First District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
Westview Ave |
Paving, water
services |
Westhampton |
As needed |
As needed |
4900 blk W
Franklin St |
Sewer service
replacement |
Willow Lawn |
As needed |
95% complete |
4600 blk
Bromley Lane |
Sewer repairs |
Willow Lawn |
Closed during the day |
30% complete,
all week |
300 blk Oak
Lane |
Sewer service
replacements, manhole invert repair |
Mary Munford |
As needed |
40% complete |
3400 Park
Avenue |
Sewer
mainline replacement in alley |
Museum
District |
As needed |
15% complete |
Sulgrave Road
at Gun Club |
Gas main |
Windsor Farms |
As needed |
As needed |
Second District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
W Clay at
Goshen |
paving |
Carver |
As needed |
As needed |
W Leigh at
Kinney |
Water main
work |
Carver |
As needed at night |
As needed |
Third District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
Moss Side
Avenue |
Dig out for
water services and paving |
Ginter Park |
As needed |
As needed |
1600 blk
Front St |
Sewer main
and service replacement |
North
Highland Park |
Closed to thru traffic |
All week |
Willow at
Althea |
Water
services in alley |
Highland Park
Southern Tip |
As needed |
As needed |
2909
Northumberland Ave |
Sewer service
replacement |
Virginia Union,
North Barton Heights |
As needed |
95% complete |
800 blk Oak
Park Ave |
Sewer repairs |
John
Marshall, Ginter Park |
Closed during the day |
2% complete,
all week |
Fourth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
None reported |
|
|
|
|
Fifth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
W 31st
St at Forest Hill |
Gas services,
clean up |
Woodland
Heights |
As needed |
As needed |
2000 W Cary
St |
Sewer service
replacements |
The upper Fan |
Eastbound left lane closed during the
day |
95% complete, all week |
2000 blk
Walker St |
Mainline
sewer repair and replacements |
Byrd Park
Historic District |
As needed |
80% complete |
301-321 W 20th
St |
New gas
services |
Swansboro |
As needed |
As needed |
1400 blk W 30th |
Gas services |
Woodland
Heights |
As needed |
As needed |
Sixth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
1301 E Cary
St |
Manhole
rehab, cavitation repair |
Downtown
Shockoe Slip |
As needed |
88% complete |
400 Tredegar
St |
Ongoing
bypass pumping |
Gambles Hill |
As needed |
ongoing |
Seventh District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
N 35th
at O St |
Cavitation
repairs |
Chimborazo |
As needed |
10% complete |
Rawlings St
at Bunn Ave |
Cavitation
repairs |
Montrose
Heights |
As needed |
Scheduled to
start |
Eighth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
2300 blk
Ingram Ave |
Milling and
paving |
Oak Grove,
Hillside Court |
As needed |
90% complete |
Transport
Street |
Gas main
renewal |
Parnell
Industrial Area |
As needed |
As needed |
Ninth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
Whitehead
Road |
Gas main |
Worthington
Farms, Swanson, Warwick, Pocoshock |
As needed |
As needed |
5348 White
Oak Drive |
Water main |
Piney Knolls |
As needed |
As needed |