Monday, October 4, 2021

Public Utilities Street Work Week of Oct 4, 2021

 

   

DPU Street Work Week of Oct. 4, 2021

*Completion estimates and closings are weather permitting

For emergency closings and daily locations, follow @DPUstreetnews on Twitter

First District

Location

Work

Area Impacted

Traffic Control

Days Closed*

6500-6900 blks Three Chopt Road from Honaker to Kensington

Sewer main installation

Bandy Field

Northbound lane closed

50 days

6213 Tapoan Road

Sewer mainline replacement

Three Chopt

As needed

50% complete

4818 Grove Ave

Sewer service replacement

Mary Munford

As needed

90% complete

200 blk W Hillcrest Ave

Sewer service replacement

Mary Munford

As needed

Scheduled to start

Rothesay Circle at Portland Place

Gas main

Windsor Farms, Carillon

As needed

As needed

Windsor Way at Cambridge

Paving

Windsor Farms

As needed

As needed

200-210 W Hillcrest Ave

Sewer service replacements

Lockgreen

As needed

Scheduled to start

W Oxford Circle at Coventry

Gas main

Windsor Farms

As needed

As needed

4500 blk Coventry Road

Gas services

Windsor Farms

As needed

As needed

Westmoreland at Grove

Paving

Colonial Place

As needed

As needed


Second District

Location

Work

Area Impacted

Traffic Control

Days Closed

222 W Marshall St

Steel plates over Collapsed storm drain for DPW

Jackson Ward

Steel plates

As needed

Norton St at Catherine

Gas main

Carver

As needed

As needed

W Marshall at Belvidere toward Brook

Milling and overlaying plaza, intersection mural, parklet, intersection crosswalks

Carver, Jackson Ward

As needed at night

1-2 weeks

100 blk N Plum St

Sewer service replacement

The Fan

As needed

88% complete

400 blk N Shields Ave

Sewer service replacement

The Fan

As needed

Scheduled to start

W Leigh at Bowe St

Gas testing

Carver

As needed

As needed

1600 blk W Broad St

Vaults

The Fan

As needed

As needed

W Leigh at Norton St

Gas services

Carver

As needed

As needed

Catherine St at Kinney St

Gas services

Carver

As needed

As needed

 

Third District

Location

Work

Area Impacted

Traffic Control

Days Closed

3000-3100 Woodrow Ave

Sewer main installation

Brookland Park

Eastside alley closed

180 days

3rd St at Althea in the alley

Gas main

Highland Park Southern Tip

As needed

As needed

2600 blk Barton Avenue

gas services, asphalt

Northern Barton Heights

As needed

As needed

512 Arnold Ave

Excavation work

Highland Terrace

Road closed

Thursday-Friday

512 Fourqurean Lane

CIPP installation

Green Park

Road closed

Thursday

2800 Wellington Ave

Excavation work

Green Park

Alleyway closed

Monday-Tuesday

3107 Hawthorne Ave

Topsoil

Ginter Park Terrace

As needed

As needed

2711 Henrico Drive

Excavation work

Green Park

Closed

Monday-Tuesday

314 Essex Place

Lateral sewer excavation work

Green Park

Road closed

Wednesday-Thursday

305 E Brookland Park Blvd

Lane closures for CIPP lateral seal installation

Green Park, Highland Terrace

Lane closures

Friday

1203-1209 Rennie Ave

Sewer service replacement

Sherwood Park

As needed

55% complete


Fourth District

Location

Work

Area Impacted

Traffic Control

Days Closed

1000 blk W 47th St

Sewer replacement

Forest Hill Terrace

Closed to thru traffic

70 days

Blakemore Road at Junaluska

Water main

Westlake Hills

As needed

As needed

Huguenot Road at Monteith

Gas main

Westchester

As needed

As needed

3830 Wainfleet Drive

Drainage improvements

Huguenot

As needed

43% complete

 

Fifth District

Location

Work

Area Impacted

Traffic Control

Days Closed

W 19th at Bainbridge

Gas main

Swansboro

As needed

As needed

W 28th at Stonewall

Paving

Swansboro

As needed

As needed

600 blk W 27th St

Gas services

Swansboro

As needed

As needed

600 blk W 28th St

Sewer construction in east alley

Swansboro

Alley east closed

10 days

W 25TH, w 26TH at Semmes

Paving

Swansboro

As needed

As needed

E 31ST St at Lawson

paving

Swansboro West

As needed

As needed

2301 Amelia St

Removing failing storm line, cavitation and installing storm system area restoration

Byrd Park Maintenance Shop

As needed

25% complete

 

Sixth District

Location

Work

Area Impacted

Traffic Control

Days Closed

14th St at Mayo Bridge

Water main, saw cutting

Downtown, Old Town Manchester

As needed

As needed

1200 blk E Byrd St Hollywood interceptor

Emergency mainline repair

Downtown Shockoe Slip

As needed

56% complete, ongoing monthly pumping

1801 Commerce Road

Sewer mainline replacement

Hillside Court, Bellemeade

As needed

60% complete


Seventh District

Location

Work

Area Impacted

Traffic Control

Days Closed

N 30th at U St

paving

Woodville, Church Hill North

As needed

As needed

3100 blk E Main St

Libby Hill

Sewer main replacement

As needed

Scheduled to start

Fairfield Ave at Kane St

Gas main

Creighton

As needed

As needed

Jefferson Avenue

Paving

Union Hill, Church Hill

As needed

As needed


Eighth District

Location

Work

Area Impacted

Traffic Control

Days Closed

2800-A North Hopkins Road

Service replacement, tie-in

Maury

As needed

Scheduled to start pending on-site inspection

 

Ninth District

Location

Work

Area Impacted

Traffic Control

Days Closed

Worthington Road

asphalt

Worthington

As needed

As needed

4221 Dorset Road

Sewer service replacement

Cottrell Farms

As needed

Scheduled to start

Snead Road at Kendall

paving

Piney Knolls

As needed

As needed