First District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Radford Ave

Gas renewed services

Monument Ave Park

As needed

As needed

Intersection of N Wilton at Matoaka Road

Drainage improvements

Westhampton

As needed

Delayed to June 1

Lockgreen Circle

Asphalt, gas line renewal

Lockgreen

As needed

As needed

304 Seneca Road

Sewer repairs

Westhampton

As needed

45% complete

11 Canterbury Road

Sewer service replacement

Windsor Farms

As needed

85% complete

3900 blk Exeter Road

Sewer mainline replacement

Windsor Farms

As needed

5% complete

5501 Cary Street Road

Excavation work, repairs, steel plates, restoration of sinkholes

Carytown

Eastbound lane closed 9-4 daily

June 1-3

 

Second District

Location

Work

Area Impacted

Traffic Control

Days Closed*

900 blk W Clay St

Gas services

Carver

As needed

As needed

400 N Madison St

Sewer mainline repair

Jackson Ward

As needed

82% complete

Catherine St at Hancock

Gas main

Carver

As needed

As needed

6 W Jackson St

Sewer service replacement

Jackson Ward

As needed

90% complete

N 1st St over I-95

Bridge replacement

Jackson Ward, Gilpin Court

Detours

TBD

Pulliam Road

New gas main

Jackson Ward

As needed

As needed


Third District

Location

Work

Area Impacted

Traffic Control

Days Closed*

3600 Noble Avenue

Sewer replacement

Ginter Park

As needed

90% complete

911 N 2nd St

Sewer service replacement

Gilpin, borders on 6th District

As needed

95% complete

3400 blk Griffin Ave

Excavation work

Edgewood

Alley closed

Monday

2600 Hawthorne Ave

Excavation work

Northern Barton Heights

Alley closed

Tuesday-Friday

Tazwll St

Gas main renewal

Norther Barton Heights

As needed

As needed


Fourth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Blakemore Road Hagueman

Water main

Westlake Hills

As needed

As needed

5204 Devonshire Road

Sewer service replacements and mainline repair

Westover Hills

As needed

90% complete

 

Fifth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

W 28th, W 29th, W 30th

Paving around area

Woodland Heights

As needed

As needed

3015 Midlothian Tpke

Sewer service replacement

Reedy Creek

As needed

90% complete

 

Sixth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

N 9th St between E Broad and E Grace

Building construction, asphalt, clean up, hydrant removal

Capitol District

Closed

Until October 2022

Oliver Hill Way

Water main

Whitcomb

As needed

As needed

E Clay at N 8th

Steel plates

Downtown

As needed

As needed

 

Seventh District

Location

Work

Area Impacted

Traffic Control

Days Closed*

N 31st at Q St

Gas main

Church Hill North

As needed

As needed

500-700 blks N 26th St

Sewer repairs

Church Hill

As needed

50% complete

2200 blk N 26th

Gas services

Fairfield

As needed

As needed

 

Eighth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Gunn St

Water main testing

Bellmeade

As needed

As needed

2401 Dale Ave

Sewer service replacement

Davee Gardens

As needed

99% complete


Ninth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Clearfield St at Kendall

Gas main

Piney Knolls

As needed

As needed

Pierpont Road

Water services

Worthington Farms

As needed

As needed