DPU Street Work Week May
17, 2021
*completion estimates
and closings are weather permitting
First District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed* |
6800 blk Hanover Road |
Sewer replacement |
Bandy Field Nature Park |
Closed for construction |
153 days |
Oxford Road at Conventry |
Paving |
Windsor Farms |
As needed |
As needed |
Coventry at Oxford |
Paving |
Windsor Farms |
As needed |
As needed |
Coventry Road betw
Berkshire and Calycanthus |
Gas main |
Windsor Farms |
As needed |
As needed |
Second District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed |
Kinney St at W Leigh |
Gas main |
Carver |
As needed |
As needed |
900 Brook Road, Brook at
Marshall |
Main |
Chamberlayne Industrial
Center |
As needed |
As needed |
1000 blk W Leigh St |
Gas services |
Carver |
As needed |
As needed |
Third District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed |
Seminary Ave at
Northumberland |
Gas renewal |
Virginia Union, Northern Barton Heights |
As needed |
As needed |
1017 Rennie Ave |
Test holes |
Ginter Park Terrace |
As needed |
As needed |
Fourth District
Location
|
Work
|
Area Impacted
|
Traffic Control
|
Days Closed
|
None known
|
|
|
|
|
Fifth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed |
Lawson St at E 32nd |
Gas main |
Swansboro West |
As needed |
As needed |
Hillcrest Road at Stonewall |
Gas main |
Forest Hill |
As needed |
As needed |
3200 blk Lawson St |
Gas services |
Swansboro West |
As needed |
As needed |
Sixth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed |
3rd at Chestnut St |
Gas services |
Highland Park Southern Tip |
As needed |
As needed |
Seventh District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed |
None known |
|
|
|
|
Eighth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed |
E 11th at
Bainbridge |
Gas main |
Blackwell |
As needed |
As needed |
Ninth District
Location |
Work |
Area Impacted |
Traffic Control |
Days Closed |
Blakemore Road |
Water testing |
Worthington Farms |
As needed |
Started April 12, 2021 |
McDowell Road |
Asphalt, water main |
Worthington Farms |
As needed |
Started Oct 1 2020 |
Windcroft Road |
Asphalt paving |
Worthington Farms |
As needed |
Started 1/20/2020 |
6500 blk Hull St |
Gas main |
Elkhardit |
As needed |
As needed |
5000 blk Snead Road |
Gas main |
Piney Knolls |
As needed |
As needed |