Lane Closure at 4615 Fitzhugh Avenue
Date: Thursday, March 19, 2015
Time: 7:30 a.m. - 4 p.m.
Closure: One lane at 4615 Fitzhugh Ave
Work: Sanitary and Storm Sewer work. DPU Contractor GL Howard is replacing
a sewer lateral. Surface treatment was delayed due to asphalt production issues. Only
asphalt work remains and is scheduled to be complete by March 19,
Impact: There will be one lane closed during asphalt placement during work hours, only.