Project status update
All drainage structures and storm sewer pipes have been
installed. The remaining items that the contractor is working on include the
following:
1.
Sub-grade preparation for asphalt paving
2.
Concrete valley gutter form and pour at north
end of Tiber Lane
3.
Asphalt paving installation
4.
Driveway surface restoration
5.
Finish grading for areas in right-of-way
adjacent to the road
6.
Seed / fertilizer / straw for grass areas
It is estimated that the project will be substantially
complete by end of the March with final completion coming one to two weeks
beyond that time.
Paving Operations
The contractor is planning to pave Tiber Lane on one day during
the latter part of the week next week weather permitting. Once an exact day and
time have been established for paving I will follow-up with another email to
make everyone aware.
The paving operation will take place during an estimated four hour time period occurring around 9 a.m. or shortly thereafter to allow residents
to leave the neighborhood for work. During the paving no vehicles or
pedestrians will be allowed on the road. Once the four hour paving operation is
complete, residents will be allowed to drive on the road surface almost
immediately. To be clear, the asphalt will go down in the morning and vehicles
will be able to drive on it later that same day.
It is recommended, if at all possible, that those with
property access concerns park along Wesley Road prior to the start of the paving. Once paving begins it may be difficult to access or leave your
property with your vehicle during the four hour paving process. Again, once paving
is done vehicles will be able to drive on the road surface almost immediately.