Monday, August 1, 2022

DPU Street Work for Week of Aug. 1, 2022

 

First District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Intersection of N Wilton at Matoaka Road

Drainage improvements

Westhampton

As needed

68% complete

304 Seneca Road

Milling and paving

Westhampton

As needed

90% complete

3900 blk Exeter Road

Sewer mainline replacement

Windsor Farms

As needed

80% complete

526 N Arthur Ashe Blvd

Waiting for CIPP lining

Museum District, borders Second District

As needed

70% complete

Portland Place

Gas services

Windsor Farms

As needed

As needed

 

Second District

Location

Work

Area Impacted

Traffic Control

Days Closed*

400 N Madison St

Sewer mainline repair

Jackson Ward

As needed

82% complete

419 Catherine St

Sewer service  replacement

Carver

As needed

Scheduled to start

W. Cary St at S Jefferson

Underground streetlight repairs

Monroe District

Lane closures on northside travel line of W Cary betw S Madison to W Main; northbound lane closed on S Jefferson betw W Cary and and W Main, night and day. Parking lots accessible from S Jefferson

All week

Catherine St

Water services

Carver

As needed

As needed

W Leigh St

Concrete

Carver

As needed

As needed

 

Third District

Location

Work

Area Impacted

Traffic Control

Days Closed*

911 N 2nd St

Sewer service replacement

Gilpin, borders on 6th District

As needed

95% complete

Althea Street

Water renewal main in alley

Southern Barton Heights, Green Park

As needed

As needed

2014 5th Ave

Backfilling

Highland Park Southern Tip

As needed

90% complete

2900 Griffin Ave

CIPP installation

Ginter Park Terrace

Alley closed

Monday

1903 Chamberlayne Ave

Exploration and sewer point repair

Chamberlayne Industrial Center

As needed

40% complete

 

Fourth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

5200 blk Devonshire Road

Milling and paving

Westover Hills

As needed

90% complete

Chippenham Parkway at Huguenot Road

Excavation work

Oxford

Shoulder closed

Thursday-Friday

1209 N 48th St

Sewer service replacement

Forest Hill Terrace

As needed

Scheduled to start

Greenvale Drive

Water main

Westlake Hills

As needed

As needed

 

Fifth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

110 S Belmont Ave

Milling and paving

Carytown

As needed

15% complete

 

600 blk S Nansemond St

Sewer repairs

Stadium

Closed during day

All week

200 blk W 35th St

Sewer repairs

Swansboro West

Closed during day

All week

 

Sixth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

N 9th St between E Broad and E Grace

Building construction, asphalt, clean up, hydrant removal

Capitol District

Closed

Until October 2022

Gunn Street

Water pressure test, asphalt

Bellemeade

As needed

As needed

S 7th St

hydrant

Central Office District

As needed

As needed

 

Seventh District

Location

Work

Area Impacted

Traffic Control

Days Closed*

500-700 blks N 26th St

Milling and paving

Church Hill

As needed

90% complete

1108 N 32nd St

Sewer service replacement

Oakwood

As needed

45% complete

802 N 25th St

Sewer service replacement

Church Hill

As needed

80% complete

2306 Jefferson Ave

Sewer service replacement

Union Hill

As needed

30% complete

1415 National St

Sewer service replacement

Montrose Heights, Fulton

As needed

75% complete

3100 blk Wharf St

Manhole installation

Libby Hill

250 feet at the north end of Wharf Street, south of the Wharf Street Tunnel Building, closed

80 days

Oliver Hill Way

Dig out for water tie-ins, clean up

Mosby Court

As needed

As needed

3014 E Broad St

Asphalt and concrete

Church Hill

As needed

80% complete

N 28th at Creighton

Gas services

Creighton

As needed

As needed

914 State Street

Sewer service replacement

Fulton

As needed

Scheduled to start

Phaup St

Paving

Fairfield

As needed

As needed

900 blk Admiral Gravely Blvd

Sewer repairs

Fulton Bottom

Closed

All week


Eighth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

2401 Dale Ave

Milling and paving

Davee Gardens

As needed

90% complete

3200-3300 blks E Broad Rock Road

Excavation work

Broad Rock

Road closures between 33rd St and 36th St

Monday-Wednesday

3000 E Broad Rock Blvd

CIPP installation

Broad Rock

Right westbound travel lane of Hull St closed from Swansboro to Broad Rock, detouring to Hull St east and Swansboro north

Tuesday


Ninth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Clearfield at Kendall

Water tie-in

Piney Knolls

As needed

As needed

Clisby Road

asphalt

Worthington Farms

As needed

As needed

Whitehead Road

Paving

Pocoshock

As needed

As needed

Andros Road

Water testing, main

Worthington Farms

As needed

As needed