Monday, July 12, 2021

Public Utilities Street Work for Week of July 12, 2021

 

DPU Street Work Week of July 12, 2021

*completion estimates and closings are weather permitting

For emergency closings and daily locations, follow @DPUstreetnews on Twitter

First District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Southbound lane of Three Chopt from Stewart to Hanover

Sewer main replacement

Bandy Field Nature Park

Closed for construction

21 days

Berkshire at Cambridge Road

Paving

Windsor Farms

As needed

As needed

Coventry at Berkshire

Gas main

Windsor Farms

As needed

As needed

10 Canterbury Road

Gas Services

Windsor Farms

As needed

As needed


Second District

Location

Work

Area Impacted

Traffic Control

Days Closed

800 blk W Leigh St

Services

Carver

As needed

As needed

N Jefferson at Marshall

Water main

Jackson Ward

As needed

As needed

222 W Marshall St

Collapsed storm drain

Jackson Ward

As needed

As needed

Norton St at W Leigh

Gas main

Carver

As needed

As needed

1100 blk W Clay St

Paving

Carver

As needed

As needed

700 blk Kinney St

Gas services

Carver

As needed

As needed


Third District

Location

Work

Area Impacted

Traffic Control

Days Closed

2500-2700 blks Seminary Ave

PE installation, services installed and killed

Virginia Union area

As needed

As needed

Azalea Ave at Brook Road

Paving Insert bridge over I-95

John Marshall

As needed

Waiting for warmer weather

3200 Garland Ave

Gas main renewal

Brookland Park

As needed

As needed


Fourth District

Location

Work

Area Impacted

Traffic Control

Days Closed

6900 blk Forest Hill Ave

Sewer replacement

Gravel Hill

Eastbound and westbound traffic reduced to one lane each way

All week

1000 blk W 47th St

Sewer replacement

Forest Hill Terrace

Closed to thru traffic

80 days





Fifth District

Location

Work

Area Impacted

Traffic Control

Days Closed

E Blake Lane at Lawson

Gas main

Swansboro West

As needed

As needed

700 blk W 26th St

Gas services

Woodland Park

As needed

As needed

3200 blk Lawson St

PE installation

Swansboro West

As needed

As needed

Stonewall Ave at W 30th

paving

Woodland Park

As needed

As needed

Bainbridge between Dundee and W 27th

Gas services and tie-ins to sidestreets

Swansboro

As needed

Waiting on service crews

Midlothian Tpke betw W Blake and W 27th

Gas services, including tie-in to a school

Reedy Creek

As needed

As needed

W 24th-W29th

Gas services, kills, paving

Reedy Creek, Swansboro

As needed

As needed

E 32nd St at Lawson

Paving

Swansboro West

As needed

As needed

E 32nd at Hull St

Gas main

Swansboro West

As needed

As needed

W 29th at Stonewall

Gas main

Woodland Heights

As needed

As needed


Sixth District

Location

Work

Area Impacted

Traffic Control

Days Closed

None

 

 

 

 


Seventh District

Location

Work

Area Impacted

Traffic Control

Days Closed

606 N 33rd St

Sewer service replacement

Chimborazo

During the day as needed

Scheduled to begin

Kane St at Creighton Road

Gas main

Creighton, Fairfield

As needed

As needed

Phaup St from Rosetta to Nine Mile, Kane St

PE installation

Fairfield

As needed

As needed

Kane St at Fairfield Ave

Paving

Creighton

As needed

As needed


Eighth District

Location

Work

Area Impacted

Traffic Control

Days Closed

2800-A N Hopkins Road

Sewer service replacement

Maury

During the day as needed

Scheduled to begin


Ninth District

Location

Work

Area Impacted

Traffic Control

Days Closed

6220 Hull St to Chippenham

PE installation, tie-ins, services

Elkhardt

As needed

As needed

McDowell St

Water main

Worthington

As needed

As needed

Worthington Road

Water main

Worthington

As needed

As needed

Blakemore Road

Water main

Worthington

As needed

As needed

Rutherford Road

Asphalt

Worthington

As needed

As needed