DATE: Tuesday, March 31, 2015 (project underway)
TIME: 7 a.m. - 4 p.m.
LOCATION: 3100 Bradwill Rd.
WORK: Sanitary and Storm Sewer-related work. DPU Contractor Chenault are performing
drainage improvements.
IMPACT: Work is being performed in the easement and ditch area.
Tuesday, March 31, 2015
Block Closure - 2400 block of Courtland
DATE: Tuesday, March 31, 2015 (project underway)
TIME: 7:30 a.m. - 4 p.m.
LOCATION: 2403 and 2408 Courtland Street
WORK: Sanitary and Storm Sewer-related work. DPU Contractor GL Howard will be
performing cleanout and installation of storm sewer. Project t is 95 percent complete.
IMPACT: Block closed during work hours only. There is one plate in the roadway.
TIME: 7:30 a.m. - 4 p.m.
LOCATION: 2403 and 2408 Courtland Street
WORK: Sanitary and Storm Sewer-related work. DPU Contractor GL Howard will be
performing cleanout and installation of storm sewer. Project t is 95 percent complete.
IMPACT: Block closed during work hours only. There is one plate in the roadway.
3603 Meadowbridge - 3/31/15
DATE: Tuesday, March 31, 2015
TIME: 7:30 a.m. - 4 p.m.
LOCATION: 3603 Meadowbridge Road
WORK: Sanitary and Storm Sewer-related work. DPU Contractor GL Howard will be
performing cleanout and installation of storm sewer. Projec t is 95 percent complete.
IMPACT: Alternating lane closures with flaggers in place as needed to direct traffic.
Lane Closure - 7th Street
TRAFFIC ADVISORY
Mayor
Dwight C. Jones
For
Immediate Release
March
31, 2015
For
more information, contact:
Sharon
North – (804) 646-5607
Lane Closure - 7th Street
WHO:
City of
Richmond Department of Public Works
WHAT: Lane Closure
WHERE: 7th Street between Bainbridge Street and Porter Street
WHAT: Lane Closure
WHERE: 7th Street between Bainbridge Street and Porter Street
WHEN: Tuesday, March 31 until June 30
BACKGROUND: The northbound lanes in the aforementioned area will
be barricaded to allow for pedestrian use during construction. The barricades will remain in place until at
least one sidewalk on 7th Street is re-opened.
DETOUR: Motorists unable to
use the barricaded lane can drive out to Commerce Road and go around
the block to get past this point.
###
Street closure - N. Vine Street 3/31/15
DATE: Tuesday, March 31, 2015
TIME: 8 a.m. - 4:30 p.m.
LOCATION: N. Vine Street between W. Main St. and Floyd Ave.
WORK: Water Distribution will be installing a water service at address 1700 W. Main St.
IMPACT: N. Vine St. will be closed between W. Main St. and Floyd Ave.
TIME: 8 a.m. - 4:30 p.m.
LOCATION: N. Vine Street between W. Main St. and Floyd Ave.
WORK: Water Distribution will be installing a water service at address 1700 W. Main St.
IMPACT: N. Vine St. will be closed between W. Main St. and Floyd Ave.
Street Closure - N. 27th 3/31/15
DATE: Tuesday, March, 2015
TIME: 8 a.m. - 4:30 p.m.
LOCATION: 915 N. 27th St. between "O" St. and "P" St.
WORK: DPU's Water Distribution section will be renewing a lead water service at
915 N. 27th Street
TIME: 8 a.m. - 4:30 p.m.
LOCATION: 915 N. 27th St. between "O" St. and "P" St.
WORK: DPU's Water Distribution section will be renewing a lead water service at
915 N. 27th Street
Monday, March 30, 2015
Street Closure – Richmond-Henrico Turnpike
TRAFFIC ADVISORY
Richmond,
Virginia
Mayor
Dwight C. Jones
For
Immediate Release
March
30, 2015
For
more information, contact:
Sharon
North – (804) 646-5607
Street Closure – Richmond-Henrico Turnpike
WHO: City of Richmond Department of Public Works
WHAT: Street Closure
WHERE: Richmond-Henrico Turnpike from East Brookland Park Boulevard to Craigie Avenue.
WHAT: Street Closure
WHERE: Richmond-Henrico Turnpike from East Brookland Park Boulevard to Craigie Avenue.
WHEN:
Wednesday, April 1 through Friday, April 3
BACKGROUND: The aforementioned area will be closed to allow tree cutting
along the Richmond-Henrico Turnpike.
DETOUR: Heading North on Richmond-Henrico Turnpike: From East Brookland
Park Boulevard, go north on Wellington Street, west on Craigie Avenue,
then north on the Richmond-Henrico Turnpike.
Heading
South on Richmond-Henrico Turnpike: From Richmond-Henrico Turnpike, go east
on Craigie Avenue, south on Wellington Street, then enter Richmond-Henrico
Turnpike.
Friday, March 27, 2015
Road Closure - Boston Avenue
Date: Saturday, March 28, 2015
Times: 7 a.m. - 3 p.m.
Closure: Road closure on Boston Ave between 17th and 18th Streets
Work: Storm drain repair
Impact: Boston Avenue between 17th and 18tb Streets will be closed until 3pm
Road Closure - Westwood Avenue
Date: Saturday, March 28, 2015
Times: 8:00 a.m. - 3:00 p.m.
Closure: Road closure
Work: Fire hydrant replacement
Impact: Westwood Avenue between Chamberlayne and Seminary Avenues will be closed
Road Closure - Idlewood Avenue
Date: Friday, March 27, 2015
Times: 8:30 a.m. - 4:30 p.m.
Closure: Road closure
Work: Water main repair
Impact: Idlewood Avenue between S. Boulevard and S. Colonial Avenue will be closed. A detour will be set up to divert traffic down S. Boulevard around to S. Sheppard St. to give a clear route to the Downtown Expressway.
Thursday, March 26, 2015
Road Closure - Honaker Avenue
Date: Thursday, March 26, 2015
Times: 3:00 p.m. - 10:00 p.m.
Closure: Road closure
Work: Fire hydrant replacement
Impact: Honaker Avenue between Patterson and Kensignton Avenues will be closed until 10:00 p.m.
Times: 3:00 p.m. - 10:00 p.m.
Closure: Road closure
Work: Fire hydrant replacement
Impact: Honaker Avenue between Patterson and Kensignton Avenues will be closed until 10:00 p.m.
Lane Closure - Patterson Avenue
Date: Thursday, March 26, 2015
Times: 3:00 p.m. - 10:00 p.m.
Closure: Lane closure
Work: Fire hydrant replacement
Impact: 6500 block of Patterson Avenue eastbound will have one lane closed until 10:00 p.m.
Times: 3:00 p.m. - 10:00 p.m.
Closure: Lane closure
Work: Fire hydrant replacement
Impact: 6500 block of Patterson Avenue eastbound will have one lane closed until 10:00 p.m.
Lane Closure - Deepwater Terminal
Date: Thursday, March 26, 2015
Times: 8:30 a.m. - 4:00 p.m.
Closure: Lane closure
Work: Water main repair
Impact: 2800 block of Deepwater Terminal will have one lane closed until 4:00 p.m.
Times: 8:30 a.m. - 4:00 p.m.
Closure: Lane closure
Work: Water main repair
Impact: 2800 block of Deepwater Terminal will have one lane closed until 4:00 p.m.
Road Closure - Belmont Avenue
Date: Thursday, March 26, 2015
Times: 8 a.m. - 3:30 p.m.
Closure: Road closure on Belmont Avenue between Hanover and Stuart Avenues
Work: Water main repair
Impact: Road will be closed during work hours.
Times: 8 a.m. - 3:30 p.m.
Closure: Road closure on Belmont Avenue between Hanover and Stuart Avenues
Work: Water main repair
Impact: Road will be closed during work hours.
Road Closure - S. Rowland Street
Date: Thursday, March 26, 2015
Times: 8 a.m. - 4:30 p.m.
Closure: Road closure at S. Rowland Street between W Cary and Main Streets
Work: Water line repair
Impact: Road will be closed during work hours.
Times: 8 a.m. - 4:30 p.m.
Closure: Road closure at S. Rowland Street between W Cary and Main Streets
Work: Water line repair
Impact: Road will be closed during work hours.
Road Closure - E. Grace Street
Date: Thursday, March 26, 2015
Times: 8 a.m. - 4:30 p.m.
Closure: Road closure on E. Grace Street between 1st and 2nd Streets
Work: Water distribution maintenance
Impact: Road will be closed during work hours, as needed.
Times: 8 a.m. - 4:30 p.m.
Closure: Road closure on E. Grace Street between 1st and 2nd Streets
Work: Water distribution maintenance
Impact: Road will be closed during work hours, as needed.
Wednesday, March 25, 2015
Street Closings, Restrictions for Monument Avenue 10K
March 25,
2015
The Richmond Police Department asks motorists to be
mindful of runners, street closings and parking restrictions for the Ukrop’s
Monument Avenue 10K this Friday and Saturday. The events begin at 8 a.m. on
Saturday, March 28, with the Virginia 529 Kids Run. The first wave of the 10K
steps off 8:30 a.m. near Broad and Harrison streets. The 10K’s finish line is
on Franklin Street
next to Monroe Park .
Logistics of the 10K will require numerous street
closings and traffic pattern changes throughout the city beginning with parking
restrictions starting at 1 p.m. on Friday, March 27. Restrictions and closures
will continue until 3 p.m. on Saturday, March 28.
Richmond Police reminds all 10K event participants and
attendees to take advantage of parking in the decks near the start and finish
lines and to not leave any items that may tempt would-be thieves in plain view
in your vehicle, regardless of where you park.
Following are the Richmond Police closings and changes
scheduled from 5 p.m. Friday to 3 p.m.
Saturday:
·
W. Franklin Street from Laurel Street to Belvidere
Street.
Following are the Richmond Police closings and changes
scheduled from 4 a.m. to 3 p.m.
Saturday:
·
W. Broad Street – both directions - from Belvidere
Street to Lombardy Street will be closed from 4 a.m. to noon. The recommended
detour for westbound traffic on Broad is right on Belvidere , left on Leigh Street and left on Allen Avenue . The
recommended detour for eastbound traffic on Broad is left on Allen, right on
Leigh and right on Belvidere.
·
N. Belvidere - southbound lane - from W. Broad to Main
from 7 a.m. to noon.
·
Blacker Street will be closed from Monument to
Monumental from 5 a.m. to 1 p.m.
·
Canal Street between 2nd Street and Belvidere
from 5 a.m. to 3 p.m.
·
Chantilly Street between Monument and Monumental from 5
a.m. to 1 p.m.
·
W. Franklin Street between Shafer and Belvidere from 4
a.m. to 3 p.m.
·
W. Franklin Street between Stuart Circle and Shafer from
7 a.m. to 2:30 p.m.
·
W. Grace Street between Belvidere and N. Allen from 7
a.m. to noon.
·
Harrison Street from W. Marshall to Park from 4 a.m. to
2 p.m.
·
Kent Road from Wythe to Monument Avenue from 4 a.m. to 1
p.m.
·
Laurel Street from W. Main to W. Broad streets from 4
a.m. to 3 p.m.
·
Cathedral Place will be closed from Laurel to Shafer Ct from 4 a.m. to 3 p.m.
·
Harrison Street will be closed from Park to Marshall
from 4 a.m. to 2 p.m.
·
N. Lombardy Street from W. Broad to Park Ave. from 7 a.m.
to 2:30 p.m.
·
Chantilly will be closed from Monumental to Monument
from 5 a.m. to 1 p.m.
·
Park Avenue between N. Lombardy/Stuart Circle and Shafer
Court from 6 a.m. to 9 a.m.
·
Shafer Street between W. Franklin and W. Broad from 4
a.m. to noon.
·
Exit ramp from Westbound I-195 to Belvidere will be closed from 6 a.m. to 3
p.m.
·
Monument Avenue will be closed from Staples Mill Road to
Stuart Circle (Lombardy Street) from 7 a.m. to 2 p.m. The recommended detour
for eastbound traffic is left on Staples Mill, right on Broad, left on Allen,
right on Leigh and right on Belvidere. The recommended detour for westbound
traffic is right on Belvidere, left on Leigh, left on Allen and right on Broad.
There will be many street closings for all north and
south streets intersecting Monument
Avenue and Franklin Street from Staples Mill Road to Belvidere Street . Motorists are strongly
encouraged to use I-95 and I-195 to travel around the city.
In addition to the street closings, parking will be
prohibited - on both sides of the streets as posted - prior to and during the
10K on the following streets starting at the following times:
1
p.m. Friday, March 27
·
Both sides of W. Broad Street from Belvidere to Lombardy
·
Both sides of W. Franklin Street from Laurel to Belvidere
·
Harrison Street between Marshall and Park Ave.
·
N. Laurel Street between W. Main and W. Broad
3
a.m. Saturday, March 28
·
Monument Avenue from Stuart Circle to Staples Mill
·
W. Franklin Street from Stuart Circle to Shafer
·
N. Laurel Street from W. Main to W. Broad
·
Park Avenue from N. Lombardy to Shafer Court/VCU
·
Shafer Street from W. Franklin to W. Broad
·
Lombardy from Park to Monument
·
Chantilly Street from Monument to Monumental
·
Kent Road from Wythe to Monument
·
Canal Street between Belvidere and 2nd
·
Blacker from Monument to Monumental
·
N. Lombardy between W. Broad to Park
·
W. Grace from Belvidere to N. Allen
·
Eastbound side only of W. Broad between N. Lombardy and
Allen
Lane closure - 5900 Midlothian Turnpike beginning 3/25
Date: Wednesday, March 25, 2015 - Not yet determined
Times: 8 a.m. - 3:30 p.m.
Closure: Lane closure at 5900 Midlothian Turnpike
Work: Sanitary and Storm Sewer-related work. DPU Contractor Accumark is performing a closed circuit
television inspection and cleaning of the sewer collection system.
Impact: Lane will be closed during work hours, as needed. End of project has not yet been determined.
Times: 8 a.m. - 3:30 p.m.
Closure: Lane closure at 5900 Midlothian Turnpike
Work: Sanitary and Storm Sewer-related work. DPU Contractor Accumark is performing a closed circuit
television inspection and cleaning of the sewer collection system.
Impact: Lane will be closed during work hours, as needed. End of project has not yet been determined.
Lane closure Riverside Drive beginning 3/25/15
Date: Wednesday, March 25, 2015 - Not yet determined
Times: 8 a.m. - 3:30 p.m.
Closure: Lane closure from 7200 - 7400 block of Riverside Drive
Work: Sanitary and Storm Sewer-related work. DPU Contractor Accumark is performing a closed circuit
television inspection and cleaning of the sewer collection system.
Impact: Lane will be closed during work hours, as needed. End of project has not yet been determined.
Times: 8 a.m. - 3:30 p.m.
Closure: Lane closure from 7200 - 7400 block of Riverside Drive
Work: Sanitary and Storm Sewer-related work. DPU Contractor Accumark is performing a closed circuit
television inspection and cleaning of the sewer collection system.
Impact: Lane will be closed during work hours, as needed. End of project has not yet been determined.
Lane closure at 1925 Belt Blvd - 3/25/15
Date: Wednesday, March 25, 2015
Times: 7:30 a.m. - 4 p.m.
Closure: Lane closure at 1925 Belt Blvd
Work: Sanitary and Storm Sewer-related work. DPU Contractor GL Howard is performing a sewer lateral
repair.
Impact: One lane closed during work hours,.
Times: 7:30 a.m. - 4 p.m.
Closure: Lane closure at 1925 Belt Blvd
Work: Sanitary and Storm Sewer-related work. DPU Contractor GL Howard is performing a sewer lateral
repair.
Impact: One lane closed during work hours,.
Road Closure - Idlewood Avenue
Date: Wednesday, March 25, 2015
Times: 8:30 a.m. - 4:30 p.m.
Closure: Road closure
Work: Water distribution maintenance
Impact: Idlewood Avenue between S. Boulevard and S. Colonial Avenue will be closed. A detour will be set up to divert traffic down S. Boulevard around to S. Sheppard St. to give a clear route to the Downtown Expressway.
Times: 8:30 a.m. - 4:30 p.m.
Closure: Road closure
Work: Water distribution maintenance
Impact: Idlewood Avenue between S. Boulevard and S. Colonial Avenue will be closed. A detour will be set up to divert traffic down S. Boulevard around to S. Sheppard St. to give a clear route to the Downtown Expressway.
Tuesday, March 24, 2015
Lane Closure - Branders Street
TRAFFIC ADVISORY
Mayor
Dwight C. Jones
For
Immediate Release
March
24, 2015
For
more information, contact:
Sharon
North – (804) 646-5607
Lane Closure – Branders Street
WHO:
City of
Richmond Department of Public Works
WHAT: Lane Closure
WHERE: Branders Street from the gate south of the fueling station to Ancarrow’s Landing
WHAT: Lane Closure
WHERE: Branders Street from the gate south of the fueling station to Ancarrow’s Landing
WHEN: Monday, March 30 through Friday, April
3, 9 a.m. To 9 p.m.
BACKGROUND: There will be alternating lane closures in the aforementioned
area to allow for road repaving. Access
to Ancarrow’s Landing will be maintained throughout the process.
###