Monday, August 29, 2022

Public Utilities Street Work for Week of August 29, 2022

 

First District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Intersection of N Wilton at Matoaka Road

Drainage improvements

Westhampton

As needed

95% complete

5602, 5618 Patterson Ave

Sewer service installation

Westhampton

As needed

60% complete

3 Maple Ave

Exploratory mainline repair

Stonewall Court, Westhampton

As needed

45% complete

Panorama Drive

Gas main

Three Chopt

As needed

As needed

380 Lexington Ave and 5011 Patterson Ave

Sewer service replacement

Willow Lawn

As needed

40% complete

3100 blk Floyd Ave

Sewer service replacement

Museum District

Closed 8 am to 6 pm

Mon-Wednesday, 90% complete

Portland Place

Gas main

Windsor Farms

As needed

As needed

Gun Club Road

Paving

Windsor Farms

As needed

As needed

3900 blk Ellwood Ave

Sewer repairs

Colonial Place

Closed 10-4 daily

All week

 

Second District

Location

Work

Area Impacted

Traffic Control

Days Closed*

1405 W Leigh St

Sewer service replacement

Carver

As needed

80% complete

Strawberry St between Grove and Floyd

Cavitation repairs

Fan District

Closed 24 hours daily

18% complete, two weeks

W Clay at Gilmer

Water main

Carver

As needed

As needed

 

 

 

 

 

 

 

Third District

Location

Work

Area Impacted

Traffic Control

Days Closed*

3rd Ave at Front St

Milling and paving

North Highland Park

As needed

90% complete

2nd Ave at Cypress

Water main

Southern Barton Heights

As needed

As needed

Tazewell St

Asphalt

Northern Barton Heights

As needed

As needed

2121 Fendall Ave

Install new sewer and abandon old service lines

Northern Barton Heights

As needed

75% complete

0 blk W Brookland Park Blvd

Sewer repairs

Brookland Park

Closed 8-4 daily, follow new traffic pattern

All week

611 W Graham Road

Gas renewal services

Northern Barton Heights

As needed

As needed


Fourth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Greenvale Drive

Water main

Westlake Hills

As needed

As needed

Glencove Lane

Water main work

Westlake Hills

As needed

As needed


Fifth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

00 E Blake Lane

Milling and paving

Swansboro West

As needed

90% complete

W 30th at Midlothian Tpke

Gas services

Reedy Creek

As needed

As needed

 

Sixth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

N 9th St between E Broad and E Grace

Building construction, asphalt, clean up, hydrant removal

Capitol District

Closed

Until October 2022

Gunn Street

Asphalt, water services

Bellemeade

As needed

As needed

S 7th St

Water tie-in

Downtown

As needed

As needed

 

Seventh District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Oliver Hill Way

Clean up

Mosby Court

As needed

As needed

N 30th at Nine Mile Road

Gas services

Woodville

As needed

As needed

3100 blk E Main St

Sewer work

Libby Hill

Eastbound traffic detours from roundabout to Williamsburg Road to Nicholson St. Westbound detours to Nicholson to Williamsburg to the roundabout Mon-Fri 9-5.

Sept. 6-26

 

Eighth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

3416 Hull Street

Sewer service replacement

Broad Rock

As needed

90% complete

400 blk Maury St

Cavitation repairs

Old Town Manchester

As needed

Scheduled to start

Lauradale Drive

Gas main

Hickory Hill

As needed

As needed

Dundas Road

Gas main renewal

Chesterfield/Bensley

As needed

As needed


Ninth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

2500 blk Clearfield St

Concrete work

Fawnbrook

As needed

As needed

Clisby Road

Asphalt

Worthington Farms

As needed

As needed

Andros Road

Clean up, water cap

Worthington Farms

As needed

As needed