Friday, January 7, 2022

Lane Closure - North Arthur Ashe Boulevard and also Laburnum Avenue at Hermitage Road

 

Traffic Advisory
Department of Public Works

Providing a clean, safe and healthy environment

 

 

 

Richmond, Virginia
The Honorable Mayor Levar M. Stoney

cid:image002.gif@01CDF4C1.68BD8A10                                                                                                                                                     

For Immediate Release

January 7, 2022

Media Contact:
Paige Hairston – 804-646-3659 (Office)

                            804-385-0409 (Cell) 

 

    

                                            Lane Closure – Various Locations  

WHO:  City of Richmond Department of Public Works (https://twitter.com/DPW_RichmondVA) 
 
WHAT:  Lane Closure
 
WHEN:  Monday, January 10 through Friday, January 21 from 7 a.m. to 5 p.m.

WHERE: 2nd Voter District:

·         North Arthur Ashe Boulevard

·         Laburnum Avenue at Hermitage Road

BACKGROUND:  The curb lane and sidewalk will be temporarily closed to install traffic signal conduits. This work is part of the traffic signal system expansion project. 

    

###

 

 

The City of Richmond Department of Public Works (DPW) is one of only 178 currently accredited public works agencies in the United States. DPW’s portfolio comprises a wide array of services to include leaf collection; street, sidewalk and alley maintenance; trash collection; recycling; grass cutting;  graffiti removal; parking enforcement; urban forestry; street signs; traffic signals and pavement markings and civil engineering. In addition, DPW maintains upkeep on most city buildings; issues permits for working in the city’s right-of-way; manages the RVA Bike Share program and maintains the fleet of city vehicles. DPW’s operating budget comes from the general fund of the City of Richmond.  For more information about DPW services, click here or call 3-1-1.

Tuesday, January 4, 2022

Public Utilities Street Work for Week of Jan. 3, 2021

 

DPU Street Work Week of Jan. 3, 2022

*Completion estimates and closings are weather permitting

For emergency closings and daily locations, follow @DPUstreetnews on Twitter

First District

Location

Work

Area Impacted

Traffic Control

Days Closed*

104 Nottingham St

Gas services

Windsor Farms

As needed

As needed

 

Second District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Hancock St at W Clay

Gas main

Carver

As needed

As needed

W Clay at Harrison

Gas services

Carver

As needed

As needed

 

Third District

Location

Work

Area Impacted

Traffic Control

Days Closed*

3000-3100 blks Woodrow Ave

Sewer main installation

Brookland Park

Easteside alley closed

140 days

4001-4005 Hill Monument Parkway

Milling and paving

Rosedale

As needed

90% complete

3810-3812 Chamberlayne Ave

Top soil, seeding and milling in median

Washington Park

As needed

90% complete

2809 North Ave

Emergency mainline repair

Northern Barton Heights

As needed

85% complete

15-100 Overbrook Road

Gas services

Northern Barton Heights

As needed

As needed

Fendall Ave at The Terrace

Gas main

Northern Barton Heights

As needed

As needed

 

Fourth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

800-1000 blks Westover Hills Blvd

Sewer service repair construction work

Forest View

Northbound traffic reduced to one lane during the day

Tuesday-Thursday







Fifth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

2301 Amelia St

Removing failing storm line, installing storm systems area restoration

Byrd Park Maintenance Shop

As needed

93% complete

1500 blk Claiborne St

Sewer service replacement

Randolph

As needed

5% complete

204-206 S Belmont Ave

Sewer service replacements

Carytown

As needed

60% complete

 

Sixth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

None

 

 

 

 

 

Seventh District

Location

Work

Area Impacted

Traffic Control

Days Closed*

1400 blk Rogers St

Milling and paving

East End

As needed

90% complete

Tate St at N 28th

Gas main

Peter Paul

As needed

As needed

600 blk N 28th St

Gas services

Fairfield

None

As needed

N 30th at Q St

Gas main

Church Hill North

As needed

As needed

3009 M Street

Sewer service installation

Church Hill

As needed

30% complete

2320 E Marshall St

Sewer service replacement

Church Hill

As needed

15% complete

 

Eighth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

500 Circlewood Drive

Cavitation repair and exploration

Woodhaven

As needed

70% complete

2500 blk Lancelot Ave

Sewer service replacement

Parnell Industrial Area

As needed

70% complete

3000-3100 blks Walmsley Blvd

Sewer service replacement

Wamsley

As needed

80% complete

 

Goolsby Ave at Richmond Highway

Gas main

Bensley

As needed

As needed


Ninth District

Location

Work

Area Impacted

Traffic Control

Days Closed*

Weather delays