Due to replacing damaged underground sewer lines,
starting Monday April 10, E 4th Street between
Maury and Everett will be closed for up to three weeks. Traffic will be detoured
north on Everett up to E 3rd to reach interstate ramp.
Phase 2 starts when phase 1 ends, E 4th Street will
be closed between Everett and Maury, and Maury will be closed between E. 5th
and E. 4th street. Detour for travelers going north on Maury will be
onto E 5th to Albany Avenue to access interstate ramp. Phase 2 will
last up to three weeks, depending on weather conditions.