Street Closure - Tazewell Street between Overbrook and West Graham Road


Traffic Advisory
Department of Public Works



Richmond, Virginia
Mayor Levar M. Stoney
                                                                                                                                                                                        
For Immediate Release

February 28, 2018
For more information, contact:
Paige Hairston – (804) 646-3659
 

 

                       Street Closure – Tazewell Street

WHO:  City of Richmond Department of Public Works

WHAT:  Street Closure

WHEN:  Monday, March 5 and Tuesday, March 6 from 9 a.m. to 5 p.m.

WHERE: Tazewell Street between Overbrook and West Graham Road
BACKGROUND: The aforementioned area will be closed to install curb ramps at the corner of Overbrook Road and Tazewell Street. The street will reopen at the end of the day. Please use caution and follow the road signs.       
                                                                     ###

Thursday, February 22, 2018

Street Closure – North Jefferson Street between West Broad & West Grace streets


Traffic Advisory
Department of Public Works



Richmond, Virginia
Mayor Levar M. Stoney
                                                                                                                                                                                        
For Immediate Release
February 22, 2018
For more information, contact:
Paige Hairston – (804) 646-3659
 

                       Street Closure – North Jefferson Street

WHO:  City of Richmond Department of Public Works

WHAT:  Street Closure

WHEN:  Starting at 6 p.m. on Monday, February 26 and ending at 6 a.m. on Tuesday, February 27
WHERE: North Jefferson Street between West Broad and West Grace streets  
BACKGROUND: The aforementioned area will be closed to allow a crane to place materials onto the roof at 200 West Grace Street. Please use caution and follow the detour signs.        
###

Tuesday, February 20, 2018

Lane Closure – East Grace Street


Traffic Advisory
Department of Public Works



Richmond, Virginia
Mayor Levar M. Stoney
                                                                                                                                                                                        
For Immediate Release
February 20, 2018
For more information, contact:
Paige Hairston – (804) 646-3659
 

 

                       Lane Closure – East Grace Street  

WHO:  City of Richmond Department of Public Works

WHAT:  Lane Closure

WHEN:  Saturday, February 24 from 7 a.m. to 6 p.m.
WHERE: East Grace Street between 7th and 8th streets 
BACKGROUND: The sidewalk and travel lanes of the aforementioned area will be closed while a crane is used to replace cooling towers on the Verizon building at 703 East Grace Street. Please use caution and follow the road signs.       
                                                                     ###

Friday, February 9, 2018

Street Closure - 2nd Street


Traffic Advisory
Department of Public Works



Richmond, Virginia
Mayor Levar M. Stoney
                                                                                                                                                                                        
For Immediate Release
February 9, 2018
For more information, contact:
Sharon North – (804) 646-5607
 

                       Street Closure – 2nd Street

WHO:  City of Richmond Department of Public Works

WHAT:  Street Closure

WHEN:  Monday, February 12 thru Wednesday, February 14, 6 a.m. to 5 p.m.
WHERE: 2nd Street between Brown’s Island Way and Spring Street  
BACKGROUND: The aforementioned area will be closed during set-up of an on-site crane at the War Memorial project. Access to Tredegar Street will be maintained.  Through traffic should remain on the Lee Bridge.  The street will remain closed for the duration of the crane set-up. Motorist should observe signage and follow detours as needed.        
###

Friday, February 2, 2018

Street Closure – Henry Street at Marshall Street


Traffic Advisory
Department of Public Works



Richmond, Virginia
Mayor Levar M. Stoney
                                                                                                                                                                                        
For Immediate Release
February 2, 2018
For more information, contact:
Paige Hairston – (804) 646-3659
 

                       Street Closure – Henry Street at Marshall Street  

WHO:  City of Richmond Department of Public Works

WHAT:  Street Closure

WHEN: Tuesday, February 6 through Friday, February 9 from 9 a.m. to 4 p.m.
WHERE: Henry Street from Marshall Street to the mid-block alley to the north  
BACKGROUND: The aforementioned area will be closed to install a new sidewalk.  Please drive carefully and follow the detour signs.        
###

Thursday, February 1, 2018

Street Closure – Idlewood Avenue and Belvidere Street Off-Ramp - NEW Completion Date

Note: Due to weather conditions, Idlewood Avenue and the off ramp will remain closed until 4 p.m. on Tuesday, February 6.  


Traffic Advisory
Department of Public Works



Richmond, Virginia
Mayor Levar M. Stoney
                                                                                                                                                                                        
For Immediate Release

February 1, 2018
For more information, contact:
Paige Hairston – (804) 646-3659
 

                      S
treet Closure – Idlewood Avenue and Belvidere Street Off-Ramp

WHO:  City of Richmond Department of Public Works

WHAT:  Street Closure

WHEN:  Starting at 9 a.m. on Monday, January 29 through ending at 4 p.m. on Tuesday, February 6

WHERE:
·         Idlewood Avenue from Harrison to Cherry streets and
·         Belvidere Street off ramp at the I-195 Downtown Expressway  
BACKGROUND: The aforementioned areas will be closed to complete the final stages of paving and to convert two-way traffic and pavement markings for the roundabout construction at the intersection of Idlewood Avenue, Grayland Avenue and the I-195 off ramp. Please use caution and follow the detour signs.        
###

Street Closure – Bruton Road between New Kent Road and Caledonia Road


Traffic Advisory
Department of Public Works



Richmond, Virginia
Mayor Levar M. Stoney
                                                                                                                                                                                        
For Immediate Release
February 1, 2018
For more information, contact:
Paige Hairston – (804) 646-3659
 

                       Street Closure – Bruton Road

WHO:  City of Richmond Department of Public Works

WHAT:  Street Closure

WHEN:  Wednesday, February 7 from 9 a.m. to 4 p.m.
WHERE: Bruton Road between New Kent Road and Caledonia Road  
BACKGROUND: The aforementioned area will be closed to operate a crane to remove a tree from 5315 Caledonia Road. Please drive carefully and follow the detour signs.        
###